29 Mar 2006 - Press conference was held organised by MCA Seputeh. Highway construction is causing excessive noise pollution, mosquito breeding ground and frequent blackouts.
28 Mar 2006 - Representative from Biro Pengaduan Awam responded and visited the construction site. A short and brief meeting was held to determine the next step of action.
22 Mar 2006 - Finally, we receive a response from Jabatan Alam Sekitar regarding the misleading EIA report that was approved by them. [Page 1] [Page 2] [Page 3]
10 Mar 2006 - Meeting with DBKL on the cracks remedy proposal by concessionaire. General offer, terms and conditions on repairs was defined and accepted
4 Mar 2006 - Sent another letter to Biro Pengaduan Awam [Page 1] [Page 2]
23 Feb 2006 - Sent another letter to Biro Pengaduan Awam again. The 1st letter was sent in June 2005 and till today there is still no reply. We thought it was supposed to be more efficient after all the support from our Prime Minister. Our case number is 21965.
22 Feb 2006 - Miscellaneous highway related news
17 Feb 2006 - Since our Minister of Works opened his lines for complaint, naturally, we lodged our and here is the response [more]
6 Feb 2006 - Our news in merdekareview.com
11 Jan 2006 - Conducted residents briefing to announce remedial action on cracks and the future impact of traffic and safety to the residents. Attended by some 100 residents.
5 Jan 2006 - Met DBKL to discuss the findings of IKRAM report and remedial procedures to be undertaken by the concessionaire
4 Jan 2006 - Some news contribution from our website visitors
|