KL-PUTRAJAYA ELEVATED HIGHWAY 2 METRES AWAY FROM RESIDENTIAL HOUSES

AUTHORITIES BLUNDER RESULTED IN THE CONSTRUCTION OF AN ELEVATED
HIGHWAY JUST 2 METRES FROM HOMES.
MORE THAN 200 HOUSES AND 1000 RESIDENTS SAFETY AND LIVELIHOOD AFFECTED


[click here for enlarged view]

[ Home ]
[ Issues ]
Background Information

The KL-Putrajaya highway Project with 26KM length, from Kampung Pandan roundabout to Putrajaya. The concession was signed on 22 October 1997. However, since then, the project was reportedly put on hold due to the economic crisis. In early 2004,it was reported in press that the length of the highway had been shorten, parcel (1) from Kampung Pandan roundabout to Technology Park Malaysia was abolished and parcel (2) from Technology Park Malaysia to Putraja remained. However the Government has decided to revive parcel (1) at the end of 2004.

Package (5) of this Project starts from Salak South Garden, pass through an established residential area, i.e. Bandar Baru Sri Petaling and end at Bukit Jalil. The stretch in Bandar Baru Sri Petaling with approximately 1.25KM will be an elevated structure to be built on the existing road, Jalan 2/149, which has 32metres reserve width that services the residential area.

In year 1997,a knowledgeable resident had written to advise LLM to shift the alignment of the highway towards Zone N of Bandar Baru Sri Petaling, which has not been developed at that time to ensure adequate buffer zone is provided on both sides of the highway. However his advice was ignored. Besides this, few more residents have also written to LLM for information of the Project between 1998 to 2003,as usual LLM had ignored them.

In general, the awareness of this Project to the public is negligible as reported in the Environmental Impact Assessment report and Supplementary Environmental Impact Assessment dated June 1997 and April 2003 respective.

Authorities Blunder, People Suffer

 
( Click on picture to see the larger picture)

Issues With Respect To Authorities’ Approvals Of The Project

Issue No 1 - Relevant laws, acts, guidelines and regulations have not been complied.

The elevated highway on top of Jalan 2/149, Bandar Baru Sri Petaling is set back just 2.3 metres away from the existing 200+ residential houses.

  1. Under JKR guideline, a highway required a minimum width reserve of 60 meters. The existing main road, Jalan 2/149 Bandar Baru Sri Petaling has only 32 meters width reserve, which does not fulfill the above requirement.

  2. Under LLM guideline, all developments are required to have a minimun setback (buffer zone) of 19m from the “right-of-way” (ROW) of a highway. There is no buffer zone provided along Jalan 2/149 to separate the highway from the existing residential houses.

  3. Under National Land Code (Act 56 of 1965) section 5, buildings are defined as any structure erected on land. With respect to public health, safety and protection of environment, the planning guidelines required minimum separation distances measured between buildings or structures to property boundaries. The elevated building structure of the highway which set back 2metres from the property boundaries along Jalan 2/149 can never comply with any act, bylaws and guidelines.

  4. Under the Environmental Act 1972, maximum levels of noise and air pollutions are defined for residential areas. The cumulative noise and air pollution generated by the existing road and elevated highway would far exceed the levels permitted by the Act. To-date, we have yet to be convinced by the relevant authorities that mitigation measures to be taken could reduce the noise and air pollution levels to the compliance limits.

Issue No 2 – Important concepts and pertinent information were not provided in the Environment Impact Assessment (EIA) reports, which defied the objective of EIA.

  1. The two important concepts excluded from the EIA report and supplementary EIA report dated June 1997 and April 2003 respective are
    • Project options/route options : unable the assessor to examine and select the best project option/route option. In fact there were plenty of route options available at the time the Project was initiated and these options are still available. These options are

      i) Follow Besraya Highway and bypass Bandar Baru Sri Petaling.

      ii) Follow Seremban Highway and bypass Bandar Baru Sri Petaling.

      iii) Shift the alignment towards Zone N of Bandar Baru Sri Petaling, which was still undeveloped at that time to provide adequate buffer zone on both sides of the highway.

    • Public participation : valid assessment of a project on the community cannot be made without some form of public participation as public participation is the most reliable way of predicting the impact of the project on people.

  2. The pertinent information not provided in the abovementioned EIA reports are as follow:

    a) The reserve width of Jalan 2/149

    b) The setback of the elevated highway from the property boundaries at the most critical area along Jalan 2/149.Instead it mentioned that a kinder garden located along Jalan 2/149 with its backyard 8metres away from the ROW.

    c) The potential significant cumulative impacts generated by the existing road and the proposed highway.

    d) Evidence to support that these impacts are no longer significant.

Issue No 3 - The relevant authorities failed to carry out their responsibilities

When the highway Project was approved in 1997, Zone N of Bandar Baru Sri Petaling abutting Jalan 2/149 has not been developed. Amazingly, the relevant approving authorities had allowed the housing development to proceed subsequently without provision of buffer zone along the approved highway Project. The following authorities should be fully responsible for

  1. Lembaga Lebuhraya Malaysia (LLM) : failure to impose on the housing development a 19metres setback from ROW of the highway.
  2. Dewan Bandaraya Kuala Lumpur (DBKL) : failure to impose or serve requisition notice under section 30 of Town and Country Planning Act 1976 (Act172) to impose on the housing development to provide buffer zone along the proposed highway.
Summary

KL-PUTRAJAYA HIGHWAY - in chronological order
 26KM stretches from Kampung Pandan to Putrajaya
 consession signed on 22 Oct 1997
 adequate land was available then
 resident wrote letter to LLM to advice them to ensure adequate buffer zone since there is land (1997)
 project was shelved due to economic crisis
 DBKL approved housing project when they should have reserved the land for highway
 Houses built and sold to unsuspecting buyers
 Land was 'lost' in the process due to authorities blunder
 Project is bulldozed despite protest for safety
 Project is in breach of their own guidelines


Chronology of Events

As the project has direct impact to the residents in Sri Petaling, the residents have on many occasions and through many channels voiced their concerns to the relevant authorities. But, unfortunately, to-date there is no formal response provided.

The following are the sequence of events taken by the residents:

1997 – individual residents have written to the relevant authorities highlighting the possible negative impacts of the project. In their letters, they have also provided options to address the issues. One of the options was to realign the proposed alignment as it was too close to the residential areas

1998 – the residents were verbally informed that the project has been shelved due to poor economic viability.

1998 – 2002 – The residents (when called up the relevant authorities) were informed that the project has been shelved and the rest of the housing development in Sri Petaling will be built according to their plan. Hence, another zone 149K was developed and sold in 2000 – 2002 (this zone is just adjacent to the existing road Jalan 2/149 planed for the elevated highway).

Early 2003 – There was confirmation in the press by the relevant Deputy Minister that the project will by revived but the stretches from town centre to Technology Park Malaysia (TPM), that also passes through the residential areas will be abolished.

2003 – 2004 – Residents continued to write to the relevant authorities seeking confirmation on the status of the project but did not receive formal response. They were told verbally that the project is shelved.

Late 2004 till now – Upon learning that the project will be revived (through verbal response from LLM), the residents have taken the following actions:

  • Collected close to 200 signatures from the residents and attached the signatures with clarification and protest letters to the relevant authorities.
  • Sought helps from the Sri Petaling Residents Associstion (SPRA) and written formal letters stating the residents’ concerns to the relevant authorities.
  • Personally and through telephones to follow-up with the relevant authorities on the formal communications.
  • Met with the relevant authorities and highlighted the residents’ concerns.
  • Written to several press to highlight the residents’ concerns

Mid July 2005 – Construction work started on site

20 July 2005 – Met concessionaire and LLM at project site. Requested LLM to issue stop work order. Dialogue fixed on 6 Aug 2005.

23 July 2005 – Work continued and request ignored. Held a peaceful demonstration [ click here for the pictures ]

25 July 2005 – Wrote subsequent letter to address residents concerns and request for immediate stop work

5 Aug 2005 - Received reply from Lembaga Lebuhraya Malaysia addressing our queries and dialogue confirmation

6 Aug 2005 - Conducted dialogue between LLM, concessionaires and residents. Conclusion derived includes:

  1. LLM and the contractor will convey the “Temporary Stop Work” request from residents to the higher authority and revert with the status
  2. The MP of Seputeh YB Theresa Kok and Seputeh MCA Chairman Dr Sua will meet Minister to attain an amicable solution to the issues.

7 Aug 2005 – Received SMS reply from Minister of Works, Datuk Seri S. Samy Vellu to YB Theresa Kok, Member of Parliament, Seputeh

read our journals for the latest chronology

[ Home ]
[ Issues ]