Posts Tagged House cracks

Meeting with Dato Ketua Pengarah of LLM

Meeting with Dato Ketua PengarahLast week on 24 June 2009, Dato’ Ketua Pengarah of Lembaga Lebuhraya Malaysia organized a meeting to meet the residents representatives regarding the issues highlighted in our email earlier. It was a well represented meeting with relevant organizations like Kementerian Kerja Raya (KKR), Dewan Bandaraya Kuala Lumpur (DBKL), Universiti Teknologi Malaysia (UTM), highway concessionaire and of course LLM themselves.

The meeting provided a platform for us to reestablish our long forgotten struggle and reengage with LLM to seek a resolution to our issues. We were also glad that we were able to share our concerns and highlight any incorrect information that was provided to Dato’ Ketua Pengarah previously.

We presented 3 key issues of which we are seeking resolution to immediately. They are :

1. Long outstanding decision for an amicable solution
Independent studies by Biro Pengaduan Awam and Jabatan Audit Negara confirmed the flaws in the approval of the highway project which has caused a negative impact to the residents. They have recommended the Government to find a solution which included the acquisition of all the affected houses or provide compensation on any loss incurred by the affected residents.

Based on our previous survey conducted with the affected residents, the majority wanted compensation for the loss of market value and cost to mitigate air and noise pollution (eg. installing air conditioning system, double glazed windows, ionisers and exhaust fans).

2. Noise pollution far exceeded the limit approved
Sound engineer sharing expertiseWe also presented our findings where the noise levels have exceeded the approved limit stated in the condition of EIA approval.

We hope that Government is able to provide a better quality of life for the residents living next to the highway by installing noise barriers of appropriate height for both above in the elevated section and below the highway to mitigate the noise impact to the level in compliance with the EIA approval.

3. Outstanding repair work / compensation for houses with cracks
We also highlighted to Dato’ Ketua Pengarah that the repair work / compensation for houses with cracks and the monitoring work by DBKL have halted.

We believe that Dato’ Ketua Pengarah will be able to conduct a thorough review of the progress and resume the initiative to repair / compensate the cracked houses

We sent in an official letter summarizing our meeting with LLM on June 26 of which Dato’ Ketua Pengarah had replied indicating that he will be preparing a report to be sent to Ministry of Works while some of the items needs to be brought to the Minister’s attention for resolution.

We would like to thank Dato’ for looking into this matter on behalf of the affected residents and hopefully we can see the light soon.

The exact details of our letter can be found here. [page 1][page 2][page 3][page 4]

, , , , , , , , , ,

1 Comment

KL-Putrajaya Highway - Resident Update 02 - May 2006

Dear fellow residents,

First of all, for those of you who are Buddhists, we would like to wish you Happy Wesak Day.

The committee would like to inform all residents that the last day to submit the letter of complaint on house cracks to DBKL is May 31, 2006. You can either fax to DBKL directly or pass them to your street representatives which will be handed over to DBKL. After that date, your request may not be entertained. As this email may not reach everybody, please inform your neighbours of the dateline.

We would like to inform you of the following updates on our website;
a. Letters to Public Accounts Committee, DBKL and Jabatan Audit Negara,
b. Status of the 1st meeting on rectification work on two of the severely damaged houses,
c. Pictures of an incident where a the supporting steel bars for one of the pillars collapsed,
d. Outcome of our meeting with PAC and DBKL
e. Road diversion notices

Please take the time to update yourself with these events and information. Please take note of the road diversions to avoid any inconveniences to yourself.

Remember, we need all your support to keep our struggle alive. Let your neighbours know so that when we plan certain activities, we can all work together as a team. If you have any reports, news, pictures about any wrong doings during the construction, please send them to us. Our email address is admin[at]sripetaling.net

Yours Sincerely,
Sri Petaling Zone N Residents Action Committee

,

No Comments