A meeting was arranged to find a resolution to the affected houses on 17 May 2007 (Thursday). Among the key attendees include Timb. Pengarah of JKA, Ir. Tan Ken Chok, reps from LLM, IKRAM, DBKL, Contractors, Sri Petaling residents.
Among the issues discussed are :
- 3 out of the 4 houses with serious cracks have been resolved. Owners have agreed to the proposed compensation. The last one has also agreed to the proposed repair, pending the suitable time to carry out the work.
- The rest of the outstanding houses has been urged to resolve asap and set a new timeline by end June 2007.
- Proposals will be distributed to residents via the residents’ association representatives.
- Residents also brought up issues such as air pollution, noise pollution, and construction work.